Math, asked by Notes108, 10 months ago

A contractor undertaking to built a walls in 50 days. He employs 50 people for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time

Answers

Answered by alok200648
4

Answer:

25 men

  • Step-by-step explanation:
  1. At first we will find number of remaining days.
  2. Finished wall in 25 days.
  3. Then find remaining wall to be complete.
  4. By unitary method will be solved ahead.
Attachments:
Similar questions