A contractor undertaking to built a walls in 50 days. He employs 50 people for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time
Answers
Answered by
4
Answer:
25 men
- Step-by-step explanation:
- At first we will find number of remaining days.
- Finished wall in 25 days.
- Then find remaining wall to be complete.
- By unitary method will be solved ahead.