A contractor undertaking to built a walls in 50 days. He employs 50 people for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time

Answers

Answered by alok200648
4

Answer:

25 men

  • Step-by-step explanation:
  1. At first we will find number of remaining days.
  2. Finished wall in 25 days.
  3. Then find remaining wall to be complete.
  4. By unitary method will be solved ahead.