Math, asked by srejonisaha37, 9 months ago

A contractor undertook the construction of 12km road to be completed in 350 days. After employing 45 men for 200 days, only a 4 1/2 km road was completed. How many more men must be engaged to finish the work in time?
.
.
.
Pls solve this fast. Reward of 15 points

Answers

Answered by kaynat87
3

Answer:

He needs 100-45=55 men to finish the work in time.

He needs 100-45=55 men to finish the work in time.Step-by-step explanation:

He needs 100-45=55 men to finish the work in time.Step-by-step explanation:Since we have given that

He needs 100-45=55 men to finish the work in time.Step-by-step explanation:Since we have given thatNumber of men = 45

He needs 100-45=55 men to finish the work in time.Step-by-step explanation:Since we have given thatNumber of men = 45Number of days = 350

He needs 100-45=55 men to finish the work in time.Step-by-step explanation:Since we have given thatNumber of men = 45Number of days = 350Length of canal = 12 km

He needs 100-45=55 men to finish the work in time.Step-by-step explanation:Since we have given thatNumber of men = 45Number of days = 350Length of canal = 12 kmIf the number of days = 200

He needs 100-45=55 men to finish the work in time.Step-by-step explanation:Since we have given thatNumber of men = 45Number of days = 350Length of canal = 12 kmIf the number of days = 200length of canal = 4.5 km

He needs 100-45=55 men to finish the work in time.Step-by-step explanation:Since we have given thatNumber of men = 45Number of days = 350Length of canal = 12 kmIf the number of days = 200length of canal = 4.5 kmSo, we need to find the number of men.

He needs 100-45=55 men to finish the work in time.Step-by-step explanation:Since we have given thatNumber of men = 45Number of days = 350Length of canal = 12 kmIf the number of days = 200length of canal = 4.5 kmSo, we need to find the number of men.According to question, we get that

 \frac{45 \times 200}{5}  =  \frac{x \times 150}{7.5}

2000 \times 7.5 = 150x

15000 = 150x

 \frac{15000}{150}  = x

100 = x

Hence, he needs 100-45=55 men to finish the work in time.