a contractor undertook to build a road in 200 days.he employed 140 men.after 60 days he found that only 1/4 of the broad could be built.how many additional men should be employed to complete the work in time?
Answers
Answered by
5
they will have to add 10 more men to do the work in 200 day
Answered by
1
Answer:
40 men