A contractor undertook to do a certain work in 75 days and employed 60 men to do it. after 25 days he found that only one-fourth of the work was done. how many more men must be employed in order that the work may be finished in time?
Answers
Answered by
14
120 more men must be employed in order that the work will be finished in time.
PLZ MÅRK ÏT THË BRÅÏÑLĪÊST ANSWER ★ AND DROP A ♥
PLZ MÅRK ÏT THË BRÅÏÑLĪÊST ANSWER ★ AND DROP A ♥
Attachments:
Answered by
16
Answer:50 men
Step-by-step explanation:
let x more workers has to hire to complete the work in time.
as we know
m1* d1= m2 d2
so
so contractor has to hire 50 more men to complete the work.