Math, asked by aasa4404, 1 year ago

A contractor undertook to do a certain work in 75 days and employed 60 men to do it. after 25 days he found that only one-fourth of the work was done. how many more men must be employed in order that the work may be finished in time?

Answers

Answered by Akv2
14
120 more men must be employed in order that the work will be finished in time.

PLZ MÅRK ÏT THË BRÅÏÑLĪÊST ANSWER ★ AND DROP A ♥
Attachments:
Answered by vaduz
16

Answer:50 men


Step-by-step explanation:

let x more workers has to hire to complete the work in time.

as we know

m1* d1= m2 d2

so

75*60=25*60*\frac{1}{4}+50*(60+x)*\frac{3}{4}\\\\18000=1500+150(60+x)\\\\18000=1500+9000+150x\\\\150x=7500\\\\x=50

so contractor has to hire 50 more men to complete the work.