A contractor who had a work force of 630 persons undertook to complete a portion of a stadium in 14 months. He was asked to complete the job in 9 months. How many extra persons had he to employ?
Answers
Answered by
1
Answer:
620
Step-by-step explanation:
Answered by
9
Answer:
630/9 - 60
60 multiplay 14 - 980
630 - 980
350
Step-by-step explanation: