A crane on a building site lifts bricks of total mass 200 kg, initially at rest on the ground, with uniform acceleration. When the bricks are 5.0m from the ground, they have a speed of 5.0 m / s. How much work is done during this process?
Answers
Answered by
8
Answer:
w=force/ time.f=mg.m=mass,g=acceleration due to gravity.
now,m is 200 so f is 200×10=2000 neuton.
now speed=distance/time so,time=distance/speed=(5m)/(5m/s)
=1sec.
here,w=f/t so,
2000/1=2000joule
Answered by
23
Answer:
The work done during this process is 12300 J.
Explanation:
Given that,
Mass = 200 kg
Height = 5.0 m
speed =5.0 m/s
The mechanical energy is defined as,
Where, m = mass
g = acceleration due to gravity
h = height
v = speed
Put the value into the formula,
The work done is change in energy.
Hence, The work done during this process is 12300 J.
Similar questions