Math, asked by Dhananjay622, 1 year ago

A do a work in 4 day B dose in 6 day . how long will both finish the work

Answers

Answered by praveensr
1
a does the work in 4days
so in 1day he will do 1/4th work
similarly b will do 1/6th work in 1day
so both together will do the total work in.
1/1/4+1/6=24/10=2.4days

Dhananjay622: tjanks u