A does 1/2 of a piece of work in 7/2 hrs,, B does 1/4 of the remainder in 3/2 hrs, and c then finishes it in 21/4 hrs. how long would it have taken the three working together to do the works?
Answers
Answered by
0
here is the answer... is it 84/25 hours ?? or 3.36 hours