Math, asked by honeygarg3274, 1 year ago

A does 80% of work in 20 days , he then calls b and they together finish remaining work in 3 days how long b alone can do the work

Answers

Answered by Anonymous
31
37 1/2 days taken by B to complete work alone
Attachments:
Answered by wifilethbridge
28

Answer:

B can complete the work in 37.5 days

Step-by-step explanation:

We are given that A does 80% of work in 20 days

Work done by A in 20 days =\frac{80}{100}=\frac{4}{5}

Work done by A in 1 day = \frac{\frac{4}{5}}{20}=\frac{1}{25}

Since 80% is work done .

So, Remianing 20% work is done in 3 days

Work done by A and B in 3 days\frac{20}{100}=\frac{1}{5}

Work done by A and B in 1 day =\frac{\frac{1}{5}}{3}

                                                   =\frac{1}{15}

Work done by B in 1 day = \frac{1}{15}-\frac{1}{25}=\frac{2}{75}

B can complete work in \frac{75}{2}

=> B can complete the work in 75/2 days = 37.5 days

Hence B can complete the work in 37.5 days