Math, asked by JAYANTHP2426, 1 year ago

A does a work in 20 days and b doesthe same in 25 days the work together for5 days and then a left . so in what timewill b finish the rest of the work

Answers

Answered by ramsir47
1
this problem we solve by lcm method

lcm of 20 and 25 is total work

lcm = 100 unit work

they separate do

100/20 = 5 unit / days


100/25 = 4 unit / days

together = 5 + 4 = 9 unit

they together do 5 days

9 × 5 = 45 unit work done

then A left

remaining work is

100 - 45 = 55 unit

B do this in

55/4 = 13.75 days