Math, asked by prince303, 1 year ago

A does half as much work as B in three-fourth of the time if together they take 18 days to complete a work .how much time shall B take to do it?

Answers

Answered by lalithabalaranjan
0

Let B takes x days to do the work.

According to the question

A takes 2×

4

3x

=

2

3x

(A+B)s 1 days work=

18

1

then

x

1

+

3x

2

=

18

1

3x

5

=

18

1

x=

3

18×5

=30

Hence B takes 30 days to do work