A farmer can plow a field in 6 days using a tractor. His helper can plow the same field in 10 days using a small tractor. How many days will be required for the plowing, if they work together?​

Answers

Answered by pranitsaxena9064
3

it will take 4 days to plough the field

Answered by Anonymous
0

Given:

Days in which farmer can plow the field = 6

Days in which helper can plow using tractor = 10

To Find:

Days required for the plowing, if they work together

Solution:

Days in which farmer can plow the field = 1/6

Days in which helper can plow using tractor = 1/10

As per time formula -

Total work = 1/6 + 1/10

= 10 + 6/60

= 16/60

= 4/15

Total days = 3.75

Answer : The total days taken by both of them to plow the field is 3.75 days.