A farmer can plow a field in 6 days using a tractor. His helper can plow the same field in 10 days using a small tractor. How many days will be required for the plowing, if they work together?
Answers
Answered by
3
it will take 4 days to plough the field
Answered by
0
Given:
Days in which farmer can plow the field = 6
Days in which helper can plow using tractor = 10
To Find:
Days required for the plowing, if they work together
Solution:
Days in which farmer can plow the field = 1/6
Days in which helper can plow using tractor = 1/10
As per time formula -
Total work = 1/6 + 1/10
= 10 + 6/60
= 16/60
= 4/15
Total days = 3.75
Answer : The total days taken by both of them to plow the field is 3.75 days.