Math, asked by aleenach83alina, 1 year ago

A group of students volunteered to finish a construction work in 25 days. 1Q of the students did not come and the work could be finished in 35 days. The original number of students in the group were?

Answers

Answered by MianIrfan
43

Answer: there is a mistake it's not Q1, it's 10

Step-by-step explanation:

Solution:

Men Days

x 25

x-10 35

X/x-10 = 35/25

By simplify

X/x-10 = 7/5

Cross multiplication

7x - 70 = 5x

2x = 70

x = 35

Answered by darshshah1912
0

Answer:

Step-by-step explanation:

Quantitative and Discrete variable