A is 40%more efficient than b and b is 20%less efficient than
c.If a takes 6days less than c to complete the work then how much time b will takes
Answers
Answered by
0
A B. C
112 80. 100
112unit - 100 unit = 6
12 unit = 6
1unit = 0.5
B will takes 80x0.5 =40 days
Is this the correct answers tell me
112 80. 100
112unit - 100 unit = 6
12 unit = 6
1unit = 0.5
B will takes 80x0.5 =40 days
Is this the correct answers tell me