A is able to complete 1/2 of certian work in 10 days and B is able to complete 1/6 of the same work in 5 days . in how much time will the work be completed if they both work together

Answers

Answered by nirbhikzisha2026
12

Step-by-step explanation:

A do 1/2 work in 10 days

A do whole work in 10*2= 20 days

A's 1 day's work =1/20part

B do 1/6 work in 5 days

B do whole work in 5*6=30 days

B's 1 day's work =1/30part

1 day's work of A+B

=1/20+1/30

=5/60=1/12 part

1/12 part of work done by A&B in =1day

Whole work is done by A&B in=1*12=12 days

Bahut lamba tha

Please mark me as Brainliest

Answered by jayane
1

Answer:

Step-by-step explanation:

A do 1/2 work in 10 days

A do whole work in 10*2= 20 days

A's 1 day's work =1/20part

B do 1/6 work in 5 days

B do whole work in 5*6=30 days

B's 1 day's work =1/30part

1 day's work of A+B

=1/20+1/30

=5/60=1/12 part

1/12 part of work done by A&B in =1day

Whole work is done by A&B in=1*12=12 days