Math, asked by wwwsen90471, 1 month ago

A is quadriple as fast as B. If B can do a piece of work in 27 days, then find the number of days they will take to complete the work together ​

Answers

Answered by DonBoscoSchool
3

Answer:

The days they will together take to complete the work will be 54 days.

Step-by-step explanation:

27+27=54