A is thrice as efficient as B in completing work.if B does the work in 30 days how long will A take to complete it?
Answers
Answered by
52
Heya Mate !!!
Your Answer is ; 22.5 days.
≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈
Step By Step Explanation ;-
≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈≈
• Efficiency and Number of days taken are inversely proportional to each other.
=> Assume number of days taken by A =x days, then number of days taken by B =3x days (as A is thrice as efficient as B).
• According to the question ;-
=> 3x - x = 60 days, hence x = 30 days
=> SO, number of days taken by A = 30 days, and number of days taken by B = 90 days
=> Assume total units of work = LCM (30 , 90) units = 90 units
=> So, work done by A in one day = (90/30) = 3 units per day AND
=> Work done by B in one day = (90/90) = 1 unit per day.
• Hence total units done by both A and B together in one day = 4 units per day
=> So, total number of days taken by both of them = Total work / Number of units done in one day = 90 / 4 = 22.5 days.