A labour receives 1680 for 4 days work as his wages. What will be his wages, if he
works for 20 days?
Answers
Answered by
1
Wages received by labour in 4 days
= Rs. 1680
Wages received by labour in 1 day
= Rs. 1680/4
= Rs. 420
Wages received by labour in 20 days
= Rs. (20 x 420)
= Rs. 8400
Therefore, Wages received by labour if he works 20 days will be Rs. 8400.