Math, asked by mahimachoudhary01, 11 months ago

A M.E.S contractor undertake to renew the floor of a building within 40 days and immediately employ 27 men upon it. At the end of 31 days the work is only half done. How many more men should he employ to complete the work in time?​

Answers

Answered by Anonymous
6

Answer:

hiiiii

your answer is here !

Step-by-step explanation:

=> Days left are (40 – 31) = 9.

=> By chain rule,

=> total no. of men required = 27 × (31/9) = 93,

=> therefore additional men required = 93 – 27 =66 men

=> 66 men is right answer !

=> follow me !

Answered by Dhruv4886
0

The contractor should employ 66 men to complete the work on time.

Given:

The contractor undertakes to renew the floor of a building within 40 days and immediately employ 27 men upon it. At the end of 31 days, the work is only half done

To find:

How many more men should he employ to complete the work in time?​

Solution:

Formula used:

(M₁× D₁ × W₂) = (M₂ × D₂ × W₁)

Where M is the number of men,

D is the number of days and W is the work done

From the data,

At the end of 31 days, 27 men completed 1/2 of the work

Here the remaining work is 1/2 of the work and the number of days is equal to 40 - 31 i.e 9 days

Let 'x' be the number of teachers that will do the remaining work

Using the formula (M₁× D₁ × W₂) = (M₂ × D₂ × W₁)  

=>  (27 × 31 × 1/2) = (x × 9 × 1/2)  

=> (27 × 31) = (x × 9)  

=> (x)  = (3 × 31)

=> x = 93  

Initially, there are 27 men

Hence number of men required = 93 - 27 = 66

Therefore,

The contractor should employ 66 men to complete the work on time.

Learn more at

https://brainly.in/question/8856903

#SPJ3

Similar questions