A machine can cut some piece of work in 6 minutes and a man using a hand saw could do it in 18 minutes. After 4 minutes there is a power shortage and the wood must be cut by hand saw. How many minutes must the man work to complete the task?
Answers
Answered by
16
Machine can cut some piece of work in 6 minutes
So in 4 minutes , machine has done 4/6 of the job i.e. 2/3 rd
Remaining work = 1/3 rd
Man can complete the work in 18 minutes
So 1/3 rd of the work = 18/3 = 6 minutes ANSWER