Math, asked by smita021980, 10 months ago


A man can do a piece of work in 16 days. But with the help of a woman they finish the work in 12 days. How much will each get if the wages were 2400. ​

Answers

Answered by indiranitarwal786
16

Answer:

here is the answer

Step-by-step explanation:

if  the work is completed by both in 12 days, quantity of work done in one day = 1/12

 

Quantity of the work done by man in one day = 1/16

 

hence quantity of work done by woman in one day = (1/12) - (1/16) = 1/48

 

hence work ratio of man and woman = (1/16) : (1/48) = 3 : 1

 

wage of man = (2400/4)×3 = Rs.1800

wage of woman = (2400/4)×1 = Rs.600

I hope you like it please mark it brainliest