. A man do a work in 12 days working
8 h/day. If he does 6 h/ day, what would
be the number of days taken by him?

Answers

Answered by TumhaariMaut
4

See The Given Attachment...

Attachments:
Answered by adarshsinghniranjan
1

Answer:

16 days

Step-by-step explanation:

M1*D1*H1/W1 = M2*D2*H2/W2

[M=no. of men, D=no. of days, H=no. of hours, W=work done]

12*8=D*6

D=16 days