A man working 8 hours a,day takes 6 days to complete a work. How many hours a day
must he work to complete the work in 16 days?Ans is 3 Days
Answers
Answered by
0
Answer:
yes right ans 3 days
Step-by-step explanation
as hours a doubled days are divided by 2