Math, asked by shyampratapsingh2, 8 months ago

a new building needs 140 windows the windows has already instaled 35 windows if every window take 4 hours to instaled then how long will it take for him to instal the remainig windows?​

Answers

Answered by SohamPakrasi1
4

Answer:

17.5 days

Step-by-step explanation:

140-35 = 105

each take 4 hours

105x4=420 hours

420/24=17.5 days

Answered by vijayhalder031
1

Concept

Building walls typically have windows installed as vented barriers for ventilation. They make it simple and clear for individuals to see out the window. Windows provide for the admission of natural light, air, or stargazing and can enhance the attractiveness of structures.

Given

A new building needs 140 windows the windows has already installed 35 windows if every window take 4 hours to install.

To Find

We have to find the time taken to install remaining windows.

Solution

According to the problem,

Remaining windows are =140-35=105

Time taken to install one window is 4 hrs.

Therefore time taken to install remaining window is =105*4=420hrs.

Hence, ime taken to install remaining window is 420hrs.

#SPJ2