A part of road is constructed by 84 workers in 36 days.How many more workers would be required to finish the work in 21days?
Answers
Answered by
1
Answer:
it is very simple.mark me as brainliest
Step-by-step explanation:
see if worker are 84 then the day are 36 and the work done in 21 day =?worker so 84 *21/36=49 workers so 49 workers wre needed to finish the work in 21 day