A particular work can be completed by 6men and 6 women in 24days , where as the same work can be completed by 8 men and 12
women in 15 days. Find :
(i) according to the amount of work done,
one man is equivalent to how many
Answers
Answered by
1
Answer:
Given,
6men + 6 women = 24 days
⇒ 6M + 6W = 24
and, 8M + 12W =15
1)Applying, M×D = M'×D'
(6M + 6W )×24= (8M + 12W)×15
⇒( M + W) ×6×24 = (2M +3W) ×4×15
⇒( M+ W)12 = (2M +3W)5
⇒12M + 12W = 10M +15W
⇒2M = 3 W
hence, 2 men is equal to 3 women
2)now, 4M +6 W = ??
Applying M×D =M'×D'
(6M + 6W )×24 = (4M +6W ) ×D'
⇒(9W + 6W) ×24 = (6W +6W)×D' ∵2M = 3 W
⇒15W ×24 = 12W ×D'
⇒D' = 30 days
It will takes 30 days to complete the same work by 4 men and 6 women