A piece of work is completed by 45 men they completed in 90 days if there are 30 men how many days to complete the work to same work

Answers

Answered by sonudevisw
0

Step-by-step explanation:

men=45

days=90

now

45*90=30*x

x=45*90/30

45*3=175

answer 175


sonudevisw: sorry it will be 135 not 175
Answered by vaibhavgenius95
0

Answer:

135 days

Step-by-step explanation:

Explanation: