a piece of work is to be completed in 16 months if 315 men finished in 18 months how many men will be required to finish it on time​

Answers

Answered by dharshinilatha
11

Answer:

280 MEN

Step-by-step explanation:

MEN                       TIME

315 MEN                 18 MONTHS

'X' MEN                   16 MONTHS

X= 315*16/18

  = 280 MEN