A project has the following characteristics: Activity Preceding Activity Duration (Weeks) A - 5 B A 2 C A 6 D B 12 E D 10 F D 9 G D 5 H B 9 I C,E 1 J G 2 K F,I,J 3 L K 9 M H,G 7 N M 8 (a) Draw the AOA network diagram for the above project. (b) Determine critical path and identify critical activities. (c) What is the project completion time? (d) Calculate the delay possible for various activities without delaying the project completion time. (e) Will the critical path change if activity G takes 10 weeks instead of 5 weeks? If so, what will be the new critical path?
Answers
Answered by
0
Answer:
Duration (Weeks) A - 5 B A 2 C A 6 D B 12 E D 10 F D 9 G D 5 H B 9 I C,E 1 J G 2 K F,I,J 3 L K 9 M H,G 7 N M 8
Explanation:
Duration (Weeks) A - 5 B A 2 C A 6 D B 12 E D 10 F D 9 G D 5 H B 9 I C,E 1 J G 2 K F,I,J 3 L K 9 M H,G 7 N M 8 1.Fair prices for their supplies. 2.Regular and timely payment according to credit terms. 3.Reasonable terms of delivery and payment. 4.Regular orders for supply. 5.Correct information about the company's financial position. 6.Healthy and cooperative inter business relationship.
Answered by
0
Explanation:
please mark me as BRIALIST please if you are army b
Similar questions