Business Studies, asked by Ravi9155, 2 months ago

A project manager needs to determine the probability of completing a project in 80 days or less. The expected project duration is 65 days with a standard deviation of 9 days. What is the probability for completion of project in the specified time

Answers

Answered by sivasuriyamahadevi
0

Answer:

A project manager needs to determine the probability of completing a project in 80 days or less. The expected project duration is 65 days with a standard deviation of 9 days. What is the the probability for completion of project in the specified time?

a) 50%

Similar questions