A public sewer line is being installed along 80 1/4 m of road. The supervisor says that the Laborers will be able to complete 7.5 in one day .How many long will the project take to complete ?
Answers
total length labourers can complete in a day= 7.5m
total days it will take to complete= 80 1/4 ÷ 7.5 =10.7 = 11 days
It will take 11 days to complete the project.
Given,
Length of the road, l = 80 1/4 m
Amount of work done in a day, w = 7.5 m
To Find,
time taken to complete the work, n
Solution,
This problem can be solved using a very simple method.
We have been that a public sewer line is being installed along a road.
The length of the road,
⇒ l = 80 1/4 m
⇒ l = 321/4 m
⇒ l = 80.25 m
The amount of work that the laborers can complete in one day,
⇒ w = 7.5 m
We have to find the no. of days it will take to complete this project, n
That is, 7.5 m road is completed by the laborers in one day
Then, 80.25 m road is completed by the laborers in 'n' days
Mathematically, this could be written as:
Therefore, it will take 11 days to complete the project.
Read more on Brainly.in:
1. https://brainly.in/question/1594920
2. https://brainly.in/question/14024271
#SPJ3