A public sewer line is being installed along 82 1/2 m of road. The supervisor says that the labourers will be able to complete 7.5 m in one day. How long will the project take to complete?
I NEED SIMPLIFIED ANSWER
Answers
Answered by
13
Answer:
11 Days
Step-by-step explanation:
A public sewer line is being installed along 82 1/2 m of road. The supervisor says that the labourers will be able to complete 7.5 m in one day. How long will the project take to complete?
Sewer line to be installed = 82 1/2 m = 165/2 m
Sewer line installed in one day = 7.5 m = 15/2 m
Number of days sewer line will be completed = Sewer line to be installed/Sewer line installed in 1 day
=> Number of days sewer line will be completed = (165/2) /(15/2)
= 11 Days
11 days will be taken to complete the project
Answered by
0
Answer:
Hii hii nahi pta
Step-by-step explanation:
Agar pta ho to mujhe bhi btana