A pump can fill a tank with water in 2 hours. Because of a leak, it took 7/3 hours to fill the tank. The leak can drain all the water of the tank in:
Answers
Answered by
8
Work done by tank without leak in 1 hr=1/2(reciprocal)
work done by tank with leak in 1 hr=3/7
Work done by the leak in 1 hour =(1/2-3/7)=1/14
work done by tank with leak in 1 hr=3/7
Work done by the leak in 1 hour =(1/2-3/7)=1/14
Leak will empty the tank in 14 hrs.
Answered by
2
Answer: it takes 14 hours
Hope it helps