A's efficiency is 16.67% more than B's efficiency. If B takes 20 days to complete a job then find in how many days both will complete the whole job starting simultaneously?
Options
120 days
120/13 days
20 days
120/7 days
Answers
both will complete the whole job starting simultaneously in 120/13 Days
Step-by-step explanation:
B takes 20 days to complete a job
=> B's 1 day work = 1/20
A's efficiency is 16.67% more than B's efficiency
=> A's 1 day work = 1/20 + (16.67/100) *(1/20)
= 1/20 + 1/120
= 7/120
A's 1 day work = 7/120
A & B's together 1 day work = 1/20 + 7/120
= (6 + 7)/120
= 13/120
both will complete the whole job starting simultaneously = 1/(13/120)
= 120/13 Days
Learn more:
efficiency of B is two times more than efficiency of A.both started ...
https://brainly.in/question/9511359
The ratio of efficiencies of A,B and C is 2:5:3 working together they ...
https://brainly.in/question/12170571
'A' completes a piece of work in 12 days. 'B' is 20% more efficient than
https://brainly.in/question/12270702
They both will complete the whole job starting simultaneously in .
Step-by-step explanation:
Given:
- A's efficiency is 16.67% more than B's efficiency.
- B takes 20 days to complete a job.
If both working together means,
They both will complete the whole job starting simultaneously in .