a sweet vendor got an order to delivery 900 boxes of an uncertain sweet in 5 days in order to complete the task he employs 3 work to work for 6 hour daily on it into days only 180 boxes have been prepared how many more work does he have to employ on it so that by working for 8 hours daily he can completed the order on time?
1)2
2)3
3)4
4)6​

Answers

Answered by subsubkingbro
0

Answer:

4

Step-by-step explanation:

i hope 70 %only if u think right u can go with my answer

hope it helps

Answered by krithikajha10
2

The answer should be 4