A takes 6 days less than the time taken by b to finish a piece of work. If both a and b together can finish it in 4 days find the time taken by b to finish the work alone.
Answers
Answered by
7
Solution :
Given :
Let the time taken by B to finish the work alone be x days
So, A can complete it in (x - 6) days.
B's one day work = 1/x
A's one day work = 1/(x - 6)
A and B together can finish it in 4 days.
(A + B)'s one day work = 1/4
According to the question,
B finished work alone = x = 2 days
A finished it in (x - 6) = 2 - 6 = - 4 days.
So, x ≠ 2 (Because Time can't be negative)
Hence,
The time taken by B to finish the work alone = 12 days.
Given :
Let the time taken by B to finish the work alone be x days
So, A can complete it in (x - 6) days.
B's one day work = 1/x
A's one day work = 1/(x - 6)
A and B together can finish it in 4 days.
(A + B)'s one day work = 1/4
According to the question,
B finished work alone = x = 2 days
A finished it in (x - 6) = 2 - 6 = - 4 days.
So, x ≠ 2 (Because Time can't be negative)
Hence,
The time taken by B to finish the work alone = 12 days.
Answered by
1
Answer:
no. of days taken by A to finish that work = x
then, no. of days taken by B to finish that work = x+6
now, work done by A in one day = 1/x and work done by B in one day = 1/x+6
now, work done by both A and B in one day,
1/x + 1/x+6 = 1/4
{(x+6)+x}/x(x+6) = 1/4
8x + 24 = x2 + 6x
x2-2x - 24 = 0
x2 -6x +4x -24 = 0
x(x-6) +4(x-6) = 0
(x+4) (x-6) = 0
so, x= 6 (neglecting x = -4)
so, time taken by B to finish the work = x+6 = 12 days
Similar questions
Computer Science,
6 months ago
Social Sciences,
6 months ago
English,
11 months ago
Physics,
11 months ago