A takes 6 hours more than (a + b +
c.Together to complete a work. B takes 1 hours more than (a + b + c)together to complete a work. C takes twice as (a +b+c) in how much time a+b wil complete the work
Answers
Answered by
12
Answer:
4/3 hrs
Step-by-step explanation:
Let say a + b + c complete work in h Hours
=> a + b + c 1 hr work = 1/h
A takes 6 hours more than (a + b + c) = h + 6 hrs
=> a's 1 hr work = 1/(h + 6)
B takes 1 hours more than (a + b + c) = h + 1
=> b's 1 hr work = 1/(h + 1)
C takes twice as (a +b+c) = 2h
=> c's 1 hr work = 1/2h
1/(h + 6) + 1/(h + 1) + 1/2h = 1/h
=> 1/(h + 6) + 1/(h + 1) = 1/2h
=> 2h(h + 1) + 2h(h + 6) = (h + 6)(h + 1)
=> 2h ( 2h + 7) = h² + 7h + 6
=> 4h² + 14h = h² + 7h + 6
=> 3h² + 7h - 6 = 0
=> 3h² + 9h - 2h - 6 = 0
=> 3h(h + 3) - 2(h + 3) = 0
=> h = 2/3
a + b 's 1 hr Work = a + b + c 's 1 hr work - c 's 1 hr work
=> a + b 's 1 hr Work = 1/h - 1/2h = 1/2h
a + b will complete work in 2h = 2 * 2/3 = 4/3 hrs
Similar questions