A takes 8 days more than'b' to complete a certain work.If both of them together can complete 90% of the work in 16 days.then find the time taken by 'B' to complete the whole work alone??
Answers
Answered by
0
Answer:
Let the time taken by B working alone = x days,
So, time taken by A working alone = (x + 8) days
∵ A complete 75% of the work,
So, the day he will work = 75% of (x+8) = 75(x+8)/100=3(x+8)/4
B has to complete 25% of work,
That is, days he will work = 25% of x = x/4
Since, B leaves the work 9 days before the work is finished,
Days for which A worked - Days for which B worked = 9 days.
3 (x+8)/4 - x/4 = 9
(2x + 24) / 4 = 9
2x = 24
X = 6
Now, x + 8 = 6 + 8 = 14
Hence, time taken by A to finish the work alone would be 14 days.