Math, asked by sinchanagujjar27, 6 months ago

A takes 9 days more than B to do a certain piece of work. Together they can do the

work in 6 days. How many days will A alone take to do the work?​

Answers

Answered by bijaylaxmiparida1080
0

Answer:

a alone will take 12 days