Math, asked by taruntamrakar, 4 months ago

A task is completed by 45 labourers in 24 days if they work 6 hours per day. How many labourers will be needed to complete the task in 15 days ifthey work for 8 hours every day?​

Answers

Answered by puzzlepedia
2

Answer:

Answer : 54

Step-by-step explanation:

PUZZLE PEDIA  -------  YOUTUBE CHANNEL

Thanks for spending time with Puzzle Pedia! ♥♥

HOPE THIS WILL HELP YOU...