A team of 8 tailors stich 16 shirts in a shift of 8 hours in a garment factory. If the
owner wants a production of 28 dozens of shirts in a week from a single shift then
how many more tailors are required to be appointed ?
a) 16
b) 24
d) 112
c) 8
Answers
Answered by
0
Answer:
d) 112 tailors required to be appointed
Similar questions
Social Sciences,
5 months ago
English,
5 months ago
English,
5 months ago
History,
11 months ago
History,
11 months ago
Science,
1 year ago
Political Science,
1 year ago