A wall can be built by 6 men working 8 hours per day in 5 days. How many days will it take 4 men to build the wall if they work only 5 hours per day?
Answers
Answered by
5
Answer:It will take 12 days to complete the work
Step-by-step explanation:
M1*D1*H1/W=M2*D2*H2/W
4*9*6=6*D*3
D=4*9*6/6*3
=12