A work force of 420 men with a contractor can finish a certain piece of work in 9 months.how many extra men must he employ to complete the job in 7 months

Answers

Answered by Arslankincsem
248

Let the work that is to be done be x

Total time taken by 420 men to complete the certain piece of work = 9 months

X = 420 * 9 = 3780

Total number of men required to complete the same work in 7 months = x / 7

= 3780 / 7 = 540

Total number of men he need to hire = 540 – 420 = 120

Answered by kusumithavemali
57

9 months :  420 mens

7 months :    x

we have to do cross multiplication then you will get  like this ( given below)

9x = 420 * 7

x =    420 * 7

       --------------

             9

when you cancel 9 and 420 then you will be

140 * 7

-----------

    3

your answer would be = 326.6