A work is expected to be completed by 30 workers in 35 days. If 10 workers leave every every 15 days, in how many days work will be completed?
(A) 55
(B) 45
(C) 40
(D) none of these
Answers
Answered by
0
Answer:
the answer will be A) 55 days