A Work is to be finished in 12 days by 20 workers. After 8 days it is found that only 1/2 part of the work has been done. How many more workers should now be engaged in order to finish job in time.












Answers

Answered by haridasan85
3

Answer:

8. 20

4. . x

x=8x20/4=40

40-20 = 20

20 workers add I. Should be engaged

Answered by sprao53413
2

Answer:

Please see the attachment