a work twice as fast as B. if B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in?
Answers
Answered by
5
Hi
Days taken by B to complete work = 12 days
As A is faster than B, so he will finish the same work before 12 days i.e. before B which is = 12/2 = 6
Hence A will finish in 6 days.
Together (A+B ) will finish work in = (6+ 12 )/2
= 18/2
= 6 days
Thanks
Hope it helped