A works at a speed 2times than B so that b takes 50 days more than a to complete a piece of work. Find the number of days required by both a and b to complete the Work
Answers
Answered by
0
A works at a speed 2 times the speed B.
efficiency ratio of A : B = 2:1
A took x days to complete a work
B took (x + 50) days to complete a work
Total work = no. of days * efficiency
A complete a work in 50 days
B complete a work in 100 days
if A works at a speed 2 times more than B.
efficiency ratio of A : B = 3:1
A took x days to complete a work
B took (x + 50) days to complete a work
Total work = no. of days * efficiency
A complete a work in 25 days
B complete a work in 75 days
(I'm little bit confused with the question. efficiency more than or 2 times the speed. so I add both cases)