According to a plan, a team of woodcutters decided to harvest 216 cubic metre of wheat in several days. in the first three days, the team fulfilled the daily assignment, and then it harvested 8 cubic metre of wheat over and above the plan every day. therefore, a day before the planned date, they had already harvested 232 cubic metre of wheat. to harvest 216 cubic metre of wheat 2 days before the planned date, how many cubic metres of wheat must be harvested by team over and the above the plan every day after first three days?
Answers
Answered by
10
Let the planned number of days = x
Rate of work = 216/x
First 3 days, work done = 216/x* 3 = 648/x
After 3 days;
Rate = (216/x + 8) per day
One day before the planed date = x – 1
Subtract the first 3 days = x – 1 – 3 = x – 4
Total work completed = 648/x + (x-4)( 216/x + 8) = 232
Simplified and solved (See the attaached image)
x = 9
To harvest 216 cubic metre of wheat 2 days before the planned date, how many cubic metres of wheat must be harvested by team over and the above the plan every day after first three days?
First 3 days = 648/9 = 72 m3
Work remaining = 216 – 72 = 144
2 days before the planned date = 9 – 3 – 2 = 4
4 days to complete 144
Work per day = 144/4 = 36
Normal rate of work = 216/x = 216/9 = 24
The number of cubic metres of wheat must be harvested by team over and the above the plan every day after first three days
= 36 – 24
= 12 cubic metres of wheat
Rate of work = 216/x
First 3 days, work done = 216/x* 3 = 648/x
After 3 days;
Rate = (216/x + 8) per day
One day before the planed date = x – 1
Subtract the first 3 days = x – 1 – 3 = x – 4
Total work completed = 648/x + (x-4)( 216/x + 8) = 232
Simplified and solved (See the attaached image)
x = 9
To harvest 216 cubic metre of wheat 2 days before the planned date, how many cubic metres of wheat must be harvested by team over and the above the plan every day after first three days?
First 3 days = 648/9 = 72 m3
Work remaining = 216 – 72 = 144
2 days before the planned date = 9 – 3 – 2 = 4
4 days to complete 144
Work per day = 144/4 = 36
Normal rate of work = 216/x = 216/9 = 24
The number of cubic metres of wheat must be harvested by team over and the above the plan every day after first three days
= 36 – 24
= 12 cubic metres of wheat
Attachments:
Answered by
2
12 is the answer......
Similar questions