Math, asked by Archit5974, 9 months ago

Aditya takes 9 days more than his father to do a certain piece of work . Together they can do the work in 6 days. How many days will Aditya take to do that work alone.
PLZ PLZ answer std 10 from quadratic equations chapter..

Answers

Answered by MaIeficent
18

Step-by-step explanation:

\bf{\underline{\underline\red{Given:-}}}

  • Aditya takes 9 more days than his father to do a piece of work.

  • He and his father together can do the work in 6 days.

\bf{\underline{\underline\blue{To\:Find:-}}}

  • The number of days, Aditya take to do that work alone.

\bf{\underline{\underline\green{Solution:-}}}

Let the number of days Aditya takes to do the work be x

And number of days taken by his father be y

As Aditya takes 9 more days than his father to complete the work.

\rm \implies x - y = 9

\rm \implies x  =y +  9......(i)

\rm Aditya's  \: one  \: day  \: work =   \dfrac{1}{x}

\rm His \:  father's \:  one  \: day \:  work =   \dfrac{1}{y}

They together take 6 days to complete the work.

\implies \rm    \dfrac{1}{x}   + \dfrac{1}{y}  =\dfrac{1}{6}

\implies \rm    \dfrac{y + x}{xy}    =\dfrac{1}{6}

\implies \rm    y + x  =\dfrac{xy}{6}

\implies \rm    6(x + y ) ={xy}

From (i) x = y + 9

\implies \rm    6(y + 9 + y ) ={y(y + 9)}

\implies \rm    6(2y + 9 ) ={y(y + 9)}

\implies \rm   12y + 54 = {y}^{2}   + 9y

\implies \rm    {y}^{2}   + 9y - 12y - 54 = 0

\implies \rm    {y}^{2}    - 3y - 54 = 0

\implies \rm    {y}^{2}    - 9y + 6y - 54 = 0[/tex</p><p></p><p>[tex]\implies \rm    {y}(y   - 9) + 6(y - 9) = 0

\implies \rm    (y   - 9) (y + 6) = 0

\implies \rm    y = 9 \: , \:  - 6

Since the number of days should not be negative.

\implies \rm    y = 9

Since:-

\implies \rm   x -  y = 9

\implies \rm   x -  9= 9

\implies \rm   x = 18

Hence;

 \boxed{  \therefore   \rm \: Aditya \: can \: complete \: the \: work  \: in \:  18 \: days}

Answered by Anonymous
26

________________________________________

\huge\red{\underline{{\bf Question : }}}

Aditya takes 9 days more than his father to do a certain piece of work. Together they can do the work in 6 days. How many days will Aditya take to do that work alone.

\huge\red{\underline{{\bf Answer : }}}

 \large\sf\underline\green{Given:}

➛ Aditya takes 9 days more than his father to do a certain piece of work .

➛ Together they can do the work in 6 days.

 \large\sf\underline\green{To\: Find:}

➛ How many days will Aditya take to do that work alone.

 \large\sf\underline\green{Solution:}

➛ Let aditya can do work in x days.

➛ Let his father can do work in y days.

➛ Then,

x - y = 9 OR x = 9 + y

➛ Aditya's one day work = 1/x

➛ Father's one day work = 1/y

➛ Then,

 \sf\blue{\frac{1}{x}  +  \frac{1}{y}  =  \frac{1}{6} }

 \sf\blue{ \frac{x + y}{xy}  =  \frac{1}{6} }

 \sf\blue{xy = 6(x + y)}

 \sf\blue{y(9 + y) = 6(9 + y + y)}

 \sf\blue{9y +  {y}^{2}  = 54 + 12y}

 \sf\blue{{y}^{2}  - 3y - 54 = 0}

 \sf\blue{y =  \frac{3 +  \sqrt{9 + 216} }{2} }

 \sf\blue{y =  \frac{3 + 15}{2} }

 \sf\blue{y = 9, - 6}

 \sf\blue{x = 9 + y = 9 + 9  = 18 \: days}

➛ Hence, Aditya can complete work in 30 days.