After working for 8 days, Hari Ram finds that only 1/3 rd of the work has been done. He employs Satya who is 60% as efficient as Hari Ram. How many days more would Satya take to complete the work ?
A) 24 1/2 days
B) 25 3/2 days
C) 24 2/3 days
D) 26 2/3 days

Answers

Answered by Anonymous
0
1/3 ---- 8

1 -------? 
Hari can do total work in = 24 days

As satya is 60% efficient as Hari, then

Satya = 1/24 x 60/100 = 1/40

=> Satya can do total work in 40 days

1 ----- 40

2/3 ---- ? => 26 2/3 days.

Answered by deepeshsengar99
0
answer is D)
26 2/3 days